Santos CCS project
Santos CCS project
Santos CCS project
The Moomba CCS project is the largest pressure piping and welding project that we’ve tended for and won.
Working with Santos has meant that we’ve been able to upscale our business to employ more people and do some more highly skilled work, which is great for our apprentices and trainees.
It’s great that Santos has invested in South Australia for the CCS project.
It’s meant that workshops and businesses like ours can stay busy.
It is going to help South Australia reduce its carbon emissions and we’re proud to be a part of that.
Total Welds – 3,396
3396
Total Dia Inches – 14,445
14,445
No NDT Fails
Total Radiographic Tested Butt Welds – 746
Total Ultrasonic Tested Butt Welds – 98
Total Magnetic Particle – 408
Total Die Penetrant Inspection – 189
Heat Treatment466
Material Diameter Range
Carbon Steel – 15nb to 300nb
Low Temp Carbon Steel – 15nb to 250nb
Stainless Steel – 20nb to 750nb
Material Thickness Range
Carbon Steel – 3.73mm to 28.58mm
Low Temp Carbon Steel – 4.78mm to 21.44mm
Stainless Steel – 3.91mm to 23.01mm
Hydrostatic Testing of 344 Spools.
Kpa maximum38,295